Nigeria’s $1.6 billion Lekki Port nears completion

Time: 2022-08-04 09:38:53    Hits: 2228

The managing authority at Lekki Deep Sea Port has announced that

the new deep sea port is 95.56 per cent complete, as construction works are

slated to be concluded by September.

Nigeria’s $1.6 billion Lekki Port nears completion

Dredging and reclamation work is 98.43 per cent done, while work on the

quay wall is 96.07 per cent finished, according to the authority.

On 1 July, Lekki Port took delivery three Super Post Panamax Ships to Shore

(STS) cranes and 10 Rubber Tyred Gantries (RTGs) ahead of the commencement of

port operations – set to begin by the end of the year.

We are delighted to announce that the construction of Lekki Port is

now at 95.65% completion.

Our management, board of directors, shareholders, EPC Contractors

and the project manager remain focused on our objective to complete construction

by September 2022

— Lekki Deep Sea Port (@LekkiPort) August 1, 2022

The container terminal will be equipped with a 1,200-metre-long quay as

well as 13 quay cranes and will have a capacity of 2.5 million TEU.

The Lekki Deep Sea Port is being constructed by China Harbour Engineering

Company Ltd. (CHEC) and it will become the first of its kind in Nigeria upon

completion.

The $1.6 billion project was announced as part of the Nigerian federal

government’s wider plan to develop six new deep sea ports in the south-west and

south-south areas of Africa, to be carried out via

public-private-partnerships.

Government data shows that its strategic location provides Lekki Port a

distinct competitive edge over any other port facility in the West African

region.

In a recent statement, Lai Mohammed, Minister of Information and Culture,

said Lekki Deep Sea Port is expected to attract total revenues of $201 billion

to the state and federal government through taxes, royalties and duties.